Tuesday, June 12, 2007

Before and After

In August 2006 American owners winged their way back to New York, having left their Argentine pride and joy in the hands of the Redevelopers, the team transformed this character apartment into a Buenos Aires home away from home.

 

Quite a few changes were made in the renovation of this apartment :

 

From this (before) —————————–> to this (after)

In the end, a substantial change and incremental value add.

Who did this ? Meet the Team at redevelopers.blog.com

or email redevelopers@hotmail.com

Posted by Russell at 00:00:00 | Permalink | Comments Off

Friday, November 24, 2006

Renovation complete

All renovation work complete, just awaiting installation of the doors for the kitchen cabinets

.

Posted by Russell at 00:00:00 | Permalink | Comments Off

Thursday, November 23, 2006

Front louvre blinds (celoseas)

Recently installed safety catches on the celoseas

 

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Air conditioners

All AC pipes now covered with soffits

Main bedroom

Second bedroom

Living room

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Bathrooms

New travertine marble top in main bathroom


and extra electrical outlets installed in main bathroom (above) and second bathroom (below)

Posted by Russell at 00:00:00 | Permalink | Comments Off

Bedroom lighting

Installed recently

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Hall Lighting

the second bathroom gets a electric socket

 

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Monday, November 13, 2006

Nov 13 update

The final stage…

finishing the tiling of the second bathroom

sanding the newly installed reclaimed wood of the passageway

sanding the master bedroom floor

the airconditioners awaiting installation

and the first stage of the kitchen takes shape along with the cement counter tops.

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Thursday, November 2, 2006

Nov 2 update

The living room floors start to look finished…

…and the passageway shutters are refitted after being shortened

 

Posted by Russell at 00:00:00 | Permalink | Comments Off

Tuesday, October 31, 2006

Oct 31 update

Progress continues as the floors get their first preparation sanding

and the reclaimed wood is installed in the passageway

Posted by Russell at 00:00:00 | Permalink | Comments Off